Rules & controls

Business rules, automated PMO controls, action time limits (OLA) and escalation rules.

Active rules
5

Of ⁦6⁩ rules

Applied, 30 days
22

Times the rules applied themselves

Time-limit compliance
⁦77%⁩

⁦12⁩ requests past their time limit now

Automatic blocks, 90 days
27

PMO controls

Action time limits (OLA)

SLAs count working days on the work calendar and pause while a request waits on someone else.

RecordStageTime limitPauses whenComplianceOpen / breached
Change requestFirst review3 working daysWaiting on the requester⁦78%⁩7 / 2
Payment certificateRaise to payment15 working daysReturned to the vendor⁦71%⁩11 / 3
ImpedimentCritical — to resolution5 calendar days—⁦64%⁩4 / 1
Gate reviewRequest to decision10 working daysWaiting for the committee to sit⁦83%⁩6 / 0
DocumentReview and approval5 working daysReturned for changes⁦89%⁩14 / 1
Meeting actionTo closure10 working days—⁦74%⁩25 / 5

Time-limit compliance by month